Configuring Successor Relationships
Configure successor relationships to define lag or relationship type.
To configure successor relationships:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select an activity whose successor relationships you want to configure and click the Relationships detail window.
- In the Relationships detail window:
- Select a successor relationship.
- Add or remove columns as needed to configure to the detail window.
- Select an option or enter a value for each field.
- Click Save.
Related Topics
Creating Activity Relationships
Configuring Activity Relationships
Assigning Predecessor Relationships
Configuring Predecessor Relationships
Assigning Successor Relationships
Successors Section of the Relationships Section of the Activity Form Page
Showing or Hiding Columns in a Table
Configuring Activity Relationships