Assigning Predecessor Relationships
You can assign predecessor relationships to the activities in a project.
To assign a predecessor relationship:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page, select the activities to which you want to assign predecessors.
- Click Row Actions and select Assign Predecessors.
- In the Assign Relationships panel:
- Select one or more activities from the Assign Predecessors list and click Assign Predecessors.
- Click Close.
- On the Activities page, click Save.
Tips
- Only Finish to Start relationships are created in the Assign Relationships panel. To create other types of relationships create the relationships in the Gantt View. Alternatively you can create the relationships in the Assign Relationships panel and then change the relationship type manually in the Relationships detail window.
- When selecting a predecessor or successor activity, you can choose from activities in the open projects only.
Related Topics
Creating Activity Relationships
Configuring Activity Relationships
Configuring Predecessor Relationships
Assigning Successor Relationships
Configuring Successor Relationships