Selecting an Activity for Review
Select an activity for review to enable the project manager or assigned status reviewers to approve the activity when updated by a team member before the status updates are applied to the project.
To select an activity for review:
- Click Projects.
- On the Projects navigation bar, click Activities.
- On the Activities page:
- Select an activity.
- Select the Review Required option.
Note: If the Review Required option is not displayed, click Customize View and select the Columns tab, then select Review Required from the General category.
- Save your changes.
Tips
- Team member status reviews must be enabled in Project Preferences.
- If the Review Required option is not selected, status updates made by team members are approved automatically. View updates for each activity assigned to a team member in the Update History detail window.
Related Topics
About P6 Team Member Status Updates
Working with P6 Team Member Status Updates
Assigning a Status Reviewer to a WBS
Reviewing Team Member Status Updates
Viewing Team Member Status Updates History
Configuring P6 Team Member Status Update Reviews
Last Published Wednesday, July 10, 2024