Import tab of the Import/Export Projects Dialog Box of the EPS Page
Overview
Use this tab to import information to a central database.
Screen Elements
Import Type list
Determines whether the Primavera XER, Primavera XML, or Microsoft Project XML import type is used.
Currencies Import In list
Determines whether to use the base currency rate in your database, or the currency rate in the XML file for importing financial data.
Base rate: Financial data will be imported as units of the base currency in your database.
XML rate: Financial data will be imported as units of the view currency present in the XML file and converted according to the exchange rates present in the XML file and in your database.
To see this list, the currency ID and name present in the XML file must match a currency ID and name in your database and the exchange rate for that currency in the XML file must be different from the exchange rate for that currency in your database.
File field
The file to be imported.
Template list
The template to use for importing or exporting a project.
Action list
To enable this list, you must select Primavera XER or Microsoft Project XML from the Import Type list.
Determines what action to take when importing:
Create New: Determines whether the application will create a new project.
Update Existing: Determines whether to update an existing project.
Import Projects table area:
Note: To enable this table area you must select Primavera XER or Primavera XML on the Import Type list and select a file to be imported.
Project ID
Displays the Project ID of the project in the import file.
Project Name
Displays the name of the project in the import file.
Import Action
Determines what action to take when importing the project from the import file:
Create New: Determines whether the application will create a new project.
Update Existing: Determines whether to update an existing project.
Ignore: Retains data in the existing project and does not import the updated data.
Import To
Determines where the project is imported.
Financial Period Calendar field
The name of the financial period calendar to assign to the project if you choose to import the project using the Create New import action.
Baselines
Determines which baselines are imported or exported.
Manage Templates button
Opens the Manage Primavera Templates or Manage MSP Templates pane.
Import button
Imports a file with your selected options.
Getting Here
- Click Projects.
- On the Projects navigation bar, click EPS.
- Click the Actions
menu and select Import/Export Projects.
- Click the Import tab.
Related Topics
About Importing and Exporting Data
About Importing and Exporting Projects