Update Baselines Dialog Box of the Activities Page or EPS Page

Overview

Use this dialog box to update project baselines.

Screen Elements

Run Optimized option

Determines whether the application will optimize the speed of the baseline update. If you select this option and errors occur during the update, errors are not logged.

Baseline update performance is further optimized when you log in as an Admin Superuser.

Ignore Last Update Date option

Determines whether the application will update all data in the baseline, regardless of when the baseline was last updated.

When you update a baseline, the date and time are stored in the Last Update Date field, which you can view in the Baselines dialog box. Select the Ignore Last Update Date option if you plan to update different data types at different times.

Project Data tab

See: Project Data Tab of the Update Baselines Dialog Box of the Activities Page or EPS Page

Activity Data tab

See: Activity Data Tab of the Update Baselines Dialog Box of the Activities Page or EPS Page

Update Options tab

See: Update Options Tab of the Update Baselines Dialog Box of the Activities Page or EPS Page

Back button

Navigates to the previous screen.

Preview button

Opens the preview screen to enable you to view the changes which will be made if you choose to update the baseline using the options you have selected.

Update button

Updates the baseline using the options you have selected.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities or EPS.
  3. Click the Actions menu and select Define Baselines.
  4. In the Define Baselines dialog box, select a baseline and click Update Baseline.

Related Topics

About Baselines

Working with Baselines

Updating Baselines