Reject Status Updates Dialog box
Overview
Use the Reject Status Updates dialog box to reject a status update if you cannot override the values in the status update.
Screen Elements
Owner or Assignment indicator
Shows whether the status update was submitted by the owner of the activity or a resource assigned to the activity.
Activity field
The ID and name of the activity whose status was updated.
Project field
The ID and name of the project.
WBS field
The ID and name of the WBS element.
Submitting Resource: The name of the resource who made the update.
Updated Resource: The name of the resource assigned to the activity.
Update Rejection grid
The grid where you can specify the reason for rejecting changes made in the update.
Field field: The name of the field which was updated.
Change field: The value assigned to the field in the update.
Reason for Rejection field: The reason provided by the rejecting reviewer.
Step Update Rejection grid
The grid where you can specify the reason for rejecting changes made to steps in the update.
Step field: The name of the step which was updated.
Field field: The name of the field which was updated.
Change field: The value assigned to the field in the update.
Reason for Rejection field: The reason provided by the rejecting reviewer.
Comments field
The overall comments made by the reviewer about the status update.
Notify team member by email option
Determine whether to send an email to the team member who made the status update to tell them that the update was rejected.
Getting Here
- Click Approvals.
- On the Approvals navigation bar, select Status Updates.
- Select a status update and and select Reject.
Related Topics
About P6 Team Member Status Updates
Working with P6 Team Member Status Updates
Reviewing Team Member Status Updates
Viewing Team Member Status Updates History