Updating Activities

Update your activities to record your progress.

Note: The fields displayed in your view are customized by your project manager. Not all fields mentioned here are available in your view and there may be additional fields in your view not mentioned in the procedure. Discuss with your manager the fields you need to update to provide status on your assignments.

To update an activity:

  1. Select an activity.
  2. On the Status tab of the progress panel:
    1. Enter your status. For example, Time Spent, % Complete, or Remaining Duration.

      Notes:

      • If Time Left is greater than zero, the amount of time added to Time Spent will be deducted from the amount in Time Left. If the Time Left is zero, then there is no change to this field.
      • If the % Complete field is disabled, your percent complete is automatically calculated using steps.
      • A project level setting determines whether you can update Time Spent directly, or whether you Log Additional Time. If you log additional time, that time will be added to the Time Spent automatically.
    2. Update your Finish By or Expected Finish date, if necessary.
  3. On the Activity Details tab of the progress panel:
    1. Update % Complete for your assigned steps, if applicable.
  4. Select Save (Ctrl+Alt+Enter).

Tips

Step me through...

Viewing Activities

Starting Activities

Updating Activities for Other Resources

Sending Email About an Activity

Starring Activities

Completing Activities

Learn more about...

Working with Activities

Field Definitions for Dates and Work Units