Completing Activities

Mark an activity complete when you have finished your work for the activity.

To mark an activity complete:

  1. Select an activity.
  2. In the activity pane, select Mark Activity Complete (Ctrl+Alt+C).
  3. On the Status tab of the progress panel:
    1. Update the status fields.
    2. Update the Finished date if the finish date is not the scheduled Finished by date.

      Note: You cannot set the Finished date to a date past the current date.

  4. Select Save.