Related Activities

Related activities are the activities that have a logical start or end relationship with your assigned activities. Predecessor activities are required to start or finish before the selected activity has started or finished; successor activities are required to start or finish after the selected activity has started or finished. These relationships are set by your project manager in P6.

Step me through...

Viewing Predecessor or Successor Activities

Sending Email to a Predecessor or Successor Activity Owner