2.3 Activation Procedures
The procedures shown in the following table are executed inside a single maintenance window.
Either procedure 4 or procedure 5 should be executed as per the requirement. Procedure 4 should be executed when NOAM and SOAM servers for at least one DSR site are installed and configured. Procedure 5 must be repeated if one or more DSR sites are added to a DSR network and PCA is to be used on the new sites.
Procedure completion times shown here are estimates. Times may vary due to differences in database size, network configuration and loading, user experience, and user preparation.
Table 2-2 Feature Activation Execution Overview
Procedure | Elapsed Time (Hours:Minutes) | Feature Activation Execution Procedures | |
---|---|---|---|
This Step | Cum. | ||
Perform Health Check (0) | 0:01-0:05 | 0:01-0:05 |
|
Feature Activation for Entire Network (0) or Feature Activation for Newly Added Sites (0) or Feature Activation on Active NOAM (0) or Feature Activation on Standby NOAM (0) or Feature Activation on Active SOAM (0) or Feature Activation on Standby SOAM (0) |
0:10-0:40 | 0:11-0:45 |
|
Restart Process (0) |
|