2.2 Preactivation Overview

The preactivation procedures shown in the following table can be performed outside a maintenance window if required. Procedure completion times shown here are estimates. Times may vary due to differences in database size, network configuration and loading, user experience, and user preparation.

Table 2-1 Preactivation Overview

Procedure Elapsed Time (Hours:Minutes) Feature Activation Prerequisites
  This Step Cumulative  
System Topology Check 0:00-1:00 0:00-1:00
  • Verify Network Element Configuration data.
  • Verify Server Group Configuration data.
  • Analyze and plan DA-MP restart sequence.
Perform Health Check 0:01-0:20 1:01-1:20
  • Verify server status.
  • Log all current alarms.