2.2.1 Pre-feature Activation Overview

The pre-activation procedures shown in the following table can be executed outside a maintenance window if desired. Procedure completion times shown here are estimates. Times may vary due to differences in database size, network configuration and loading, user experience, and user preparation.

Table 2-1 Pre-Feature Activation Overview

Procedure Elapsed Time (Hours:Minutes) Activity Feature Activation Preparation Impact
  This Step Cum.    
System Topology Check 0:20 0:20
  • Verify Network Element Configuration data.
  • Verify System Group Configuration data.
  • Analyze and plan DA-MP restart sequence.
None
Perform Health Check 0:05 0.25
  • Verify DSR release.
  • Verify server status.
  • Log all current alarms.
None