3 Migration Checklist
This section describes migration tasks that are required to migrate from BM to VM.
Perform migration in the following sequence.
Table 3-1 Migration Sequence
| Sequence | Task | Reference |
|---|---|---|
| 1 | Prerequisite | Prerequisites |
| 2 | Task - Standby NOAM | Shutting Down Standby BM NOAM |
| 3 | Task - Active NOAM | Migrating Standby BM NOAM to VM NOAM |
| 4 | Task - Standby SOAM | Migrating BM Standby SOAM to VM |
| 5 | Task - Active SOAM | Migrating BM Standby SOAM to VM |
| 6 | Task - Upgrade DAMPs | Migrating the DAMP Server |
| 7 | Task - Upgrade IPFEs | Identifying Standby IPFE Instance |
| 8 | Task - Upgrade SBR MPs | SBR Database Migration |
| 9 | Task - Migrate SDS | Refer to SDS Migration Guide. |