Assigning a Base Calendar to a Project Calendar
Assign a base calendar to determine holidays and exceptions for the selected project calendar.
To assign a base calendar:
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Projects and click Project Calendars.
- On the Project Calendars page:
- Expand a project.
Note: If the project you need is not open, click Open Project.... Choose one or more projects and click Open.
- Select a calendar to assign a base calendar.
- In the Base Calendar area, in the Search field click Select.
- Expand a project.
- In the Select Base Calendar dialog box, select a calendar and click Select.
- Click Save.