Configuring the Standard Work Week for Project Calendars
Configure the standard work week for the calendar to set the work and nonwork days and hours for a standard work week.
To configure the standard work week:
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Projects and click Project Calendars.
- On the Project Calendars page:
- Expand a project.
Note: If the project you need is not open, click Open Project.... Choose one or more projects and click Open.
- Click on the calendar you want to modify.
- Click the Standard Work Week tab.
- Expand a project.
- On the Standard Work Week tab, right-click on a working or nonworking timeslot and use the menu options to adjust the workday. You can also resize the working time to increase or decrease the work hours.
- Click Save (Ctrl+S).
Related Topics
Assigning a Base Calendar to a Project Calendar
Setting Work Hours Per Period for a Project Calendar
Modifying Calendar Days on Project Calendars
Changing a Project Calendar to a Global Calendar
Last Published Tuesday, March 26, 2024