Summarized, Published, and Live Data Usage in P6

The data you see in P6 can be of the following types:

The following table shows which type of data is used in each area of the software.

Dashboards

Data Type

Source

Bubble charts, histograms, pie charts, score cards, side-by-side histograms, stacked histograms.

Published

  • Except costs, units, dates, durations calculated using dates, and activity counts.

Summarized

Project Performance

Published

  • Except earned value management calculations.

Summarized (using the Project baseline)

Open Requests for Resources

 

  • Roles to be staffed

Live

  • Spread data

Published

My Projects

Live

My Activities

Live

My Risks

Live

My Issues

Live

My Documents

Live

My Calendar

Live

Portfolios

Data Type

Source

Portfolio Analysis Page

Published

  • Except costs, units, dates, durations calculated using dates, and activity counts.

Summarized

Capacity Planning Page

Summarized

Performance Status Page

Published

  • Except earned value management calculations.

Summarized (using the Project baseline)

Projects

Data Type

Source

EPS Page

Live

  • Except costs, units, dates, and activity counts.

Summarized

  • Except durations.

Live (but calculated from summarized data)

Activities Page

Live

  • Except Resource Availability.

Published

Team Usage Page

Published

Assignments Page

Live

  • Except Resource Availability

Published

Issues Page

Live

Documents Page

Live

Risks Page

Live

Resources

Data Type

Source

Assignments Page

Live

  • Except Resource Availability

Published

Planning Page

Live

  • Except Resource Availability

Published

Analysis Page

Published

Administration Page

Live

Approvals

Data Type

Source

Status Updates Page

Live

Timesheets Page

Live

Reports

Data Type

Source

All data

Published