Reporting a Completed Assignment

When you finish a work assignment, if your project allows, you can mark the assignment as completed.

Note: Completing an activity in a timesheet will not apply an Actual Finish to the activity. The actual finish will be applied in the project in P6 after the Project Manager runs Apply Actuals.

To report a completed activity assignment:

  1. Select Timesheets and open a timesheet.
  2. Select an activity.

    In Classic View:

    1. Select Mark Activity Complete (Ctrl+Alt+C).

In Standard View:

  1. Enter te date the work finished in the Actual Finish column.