Location: part 2, page 3, pane 5
Pane 5 describes how to properly supply power to the Oracle PCA.
Steps:
- Review the safety guidelines. Refer to the section "Review Safety Guidelines" in the Oracle Private Cloud Appliance Installation Guide. 
- Visually inspect the appliance. - Check the rack for damage and loose or missing screws. 
- Check that cables are securely connected. 
- Verify that power cables with appropriate connectors for your power source have been supplied. 
- Check the floor tile arrangement for cable access and airflow. 
- Check the airflow that leads in to the front of the system. (See Verify Installation Requirements.) 
 
- Connect the power cords. - Open the rear door. 
- Remove the cable ties from the power cords. 
- Route the power cords to the facility receptacles either above the rack or below the flooring. - An image illustrates both cabling options. It shows a rack with power cables routed through the top, and a rack with power cables routed through the data center floor. A detail bubble in the center shows how power cords are secured in bundles. 
- Secure the power cords in bundles. 
- Plug the power distribution unit (PDU) power cords into the facility receptacles. 
 