Schedule Project Log Dialog Box of the Activities Page

Overview

Use this dialog box to view errors, warnings, and exceptions as well as basic information about the job, such as option settings and statistics.

Screen Elements

Scheduling Settings section

See Scheduling Settings Section of the Schedule Project Log Dialog Box of the Activities Page.

Statistics section

See Statistics Section of the Schedule Project Log Dialog Box of the Activities Page.

Errors section

See Errors Section of the Schedule Project Log Dialog Box of the Activities Page

Warnings section

See Warnings Section of the Schedule Project Log Dialog Box of the Activities Page.

Scheduling Results section

See Scheduling Results of the Schedule Project Log Dialog Box of the Activities Page.

Exceptions section

See Exceptions Section of the Schedule Project Log Dialog Box of the Activities Page.

Getting Here

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, and click Schedule... (F9).
  4. In the Schedule dialog box:
    1. Configure the options and select the Display scheduling log upon completion option.
    2. Click Schedule Now.