Configuring Activity Issues

Configure activity issues to account for changes since the last update on the issue.

To configure activity issues:

  1. On the  Navigation Menu, expand  Projects and click Activities.
  2. On the Activities page, select an activity and click the Issues detail window.

    Note To configure a project or WBS issue, select a project or WBS in place of an activity.

  3. In the Issues detail window:
    1. Select an issue.
    2. Select an option or enter a value for each field.
  4. On the Activities page click Save.