Configuring Activity Issues
Configure activity issues to account for changes since the last update on the issue.
To configure activity issues:
- On the
Navigation Menu, expand
Projects and click Activities. - On the Activities page, select an activity and click the Issues detail window.
Note To configure a project or WBS issue, select a project or WBS in place of an activity.
- In the Issues detail window:
- Select an issue.
- Select an option or enter a value for each field.
- On the Activities page click Save.
Related Topics
Showing or Hiding Columns in a Table