Creating Activity Issues

Create activity issues to identify problems that must be addressed before a project can be completed.

To create activity issues:

  1. On the  Navigation Menu, expand  Projects and click Activities.
  2. On the Activities page, select an activity and click the Issues detail window.

    Note To create a project or WBS issue, select a project or WBS in place of an activity.

  3. In the Issues detail window:
    1. Click  Add.
    2. Enter or select a value for the Issue Name, Priority, Status, and Responsible Manager fields.
  4. On the Activities page, click Save.

Tip

  • You cannot add an issue to a project that is checked out or locked.
  • The application automatically names the issue New Issue. Update the issue so it has a unique name.

Related Topics

About Issues

Configuring Activity Issues