Adding Values to a Report Interconnect

Access Work With Scheduled Jobs form.

You can add values to be passed through a report interconnect into a batch process when that batch process is launched. The batch process must first contain a report interconnect.

  1. On the Work With Scheduled Jobs form, select the job and then select Advanced Options from the Row menu.

  2. On the Scheduling Advanced Options form, select Parameters from the Form menu.

  3. On the Report Interconnect form, enter the values that you want to pass to the batch process when the process runs.

  4. Click OK.