Entering Work Orders Using the Planning Workbench (P13700)

Access the Work Order - Manage [work order description] form.

Work Order- Manage [work order description] form (1 of 2)

Enter, view, or revise work orders.

Select the Planning, Order Detail, Classification, Accounting, or Attachment tab to enter the relevant information.

(Release 9.2 Update) Based on the Estimated Hours and Estimated Downtime Hours on the Planning tab, the system automatically calculates the Planned Finish Date when you save the work order details.

The system compares the Estimated Hours and Estimated Downtime Hours, selects the greater value, and converts it into days using the workday calendar. These days are added to the Planned Start Date to determine the Planned Finish Date.