Processing Tab
Although processing options are set up during JD Edwards EnterpriseOne implementation, you can change processing options each time you run a program.
- 1. Changes
Enter a value to determine how changes will occur.
<Blank> means that changes will only be allowed at the package level and will apply to all servers selected.
Enter 1 to enable changes to the build definitions by individual server.
- 2. Mastering
Mark this processing option with a 1 if this process is for Mastering purposes. If the process is for all users, mark this processing option with <Blank>.
- 3. Build Verification
Mark this processing option with a 1 if the Build Verification UBE is to be run prior to building all packages. If the build verification fails, the package build UBE will not be run. Leave this processing option <Blank> if you do not want to run Build Verification.
- 4. Director or Express Mode
Use this processing option to switch between Director and Express modes.
- 5. ESU build (Tools Release 9.2.6)
Mark this processing option if this is an ESU build.
- 6. Compress Application Component use in Server Manager (Tools Release 9.2.7)
Enter 1 if you want the Compress Application Component to be automatically selected. Leave this processing option blank or enter 0 if you do not want to create the Application Component file.
- 7. Build Net Changed Objects Only (Tools Release 9.2.7)
- Enter 1 if you want to build a full package with only the business functions and tables that were changed. The specs tables will be fully built. This will shorten the build time. Leave this processing option blank or enter 0 if you want to build all objects in the full package.