Rules to Calculate Projected Final Units (HU)

You can update either the ETCU (estimate-to-complete units) or the EACU (estimate-at-completion units) field.

Note: Regardless of which field you update, the system updates the new projected final values into the BORG field of the HU ledger, and the balance/adjustment is made through the net posting field.
  • If you enter estimate-to-complete units, the system calculates HU using the formula ETCU + AU.

  • If you enter the EACU value, the system calculates difference the between EACU and AU and displays ETCU.

  • If EACU is zero, the system calculates HU using one of the two formulas AU + PU or RBLU, whichever is greater.