Method E (Estimate to Complete)

You assign method E when you want to determine the estimated amount or estimated units that are required to complete the task and to calculate projected final values. You must use the Job Progress Entry program to display the ETC (estimate-to-complete) fields.

  • Assign to header and detail accounts.

  • The system calculates PC using the formula AA / HA * 100.