Calculated Engineering Variances
This report provides the engineering variances that exist between frozen costs and current costs for each branch or item/branch combination. The report also displays details of the work order and the breakdown of the variances based on cost type.
This report contains the following components:
Engineering Variances by Branch (pie chart)
Engineering Variance Greater Than Zero - by Item/Branch (bar graph)
Engineering Variance Less Than Zero - by Item/Branch (bar graph)
Engineering Variance by Item/Branch (bar graph)
Calculated Engineering Variance by Branch (table)
The Calculated Engineering Variance by Branch table component contains drill back functionality as described in the following table:
Functionality |
Value |
---|---|
Table column containing drill back link |
Work Order Number |
Table columns passed to application |
Work Order Number |
Application called |
Production Cost Inquiry (P31022) |
Form called |
W31022A |
Version called |
ZJDE0001 |