Calculated Engineering Variances

This report provides the engineering variances that exist between frozen costs and current costs for each branch or item/branch combination. The report also displays details of the work order and the breakdown of the variances based on cost type.

This report contains the following components:

  • Engineering Variances by Branch (pie chart)

  • Engineering Variance Greater Than Zero - by Item/Branch (bar graph)

  • Engineering Variance Less Than Zero - by Item/Branch (bar graph)

  • Engineering Variance by Item/Branch (bar graph)

  • Calculated Engineering Variance by Branch (table)

The Calculated Engineering Variance by Branch table component contains drill back functionality as described in the following table:

Functionality

Value

Table column containing drill back link

Work Order Number

Table columns passed to application

Work Order Number

Application called

Production Cost Inquiry (P31022)

Form called

W31022A

Version called

ZJDE0001