Speed Actuals

Occasionally, you might need to add or change the actual values on several operations. You can use the Speed Actuals Update form to add and change the actual values on multiple operations using one form. The system displays the appropriate fields based on the type of operation that you select.

You can enter and modify most of the same information using the forms in the Speed Actuals Update program (P31B67) as you can using the Create/Edit Operations program (P31B87). However, when you use the Speed Actuates Update program, you can enter and modify information and apply changes to multiple operations.

You can select from these tabs in the Speed Actuals Update program to enter actuals:

The system retrieves and updates data from the following tables when you work with speed actuals:

  • Operation Workflow Status Map (F31B74)

  • Operation Additives (F31B84)

  • Human Resource Assignments (F31B97)

  • Blend Lot Master (F31B31)

  • Operation Vessel Assignments (F31B70)

  • Operation Header (F31B65)

  • Equipment Assignments (F31B052)

  • Operation - Vessel to Vessel ID (F31B71)

  • Operation Vessel Dips (F31B72)

Additionally, the system retrieves data from these tables:

  • Configured Operation (F31B75)

  • Base Operation Configuration (F31B73)

You can change only the Instructed Start, Instructed End, and Status fields for the operation header record.

Note: If you change the operational dependency by changing the dates, the system does not update correct amounts in the planned quantities until you click the Save and Close button.