Process

These processing options control settings that affect processing in the Project Workbench program.

1. Enter the cancelled status for tasks

Specify the status for canceled tasks. When you select Cancel Task from the Row menu, the system moves the selected task to this status. Tasks at this status appear crossed out.

2. Enter the closed status for tasks

Specify the status for closed tasks. When you select Close Task from the Row menu on the Project Workbench form, the system moves the selected task to this status. Tasks at this status appear crossed out.

3. Net Change

Specify whether net change processing is performed when you quit the Project Workbench program (P31P001). You may want to run net change processing when you have changed information, such as dates, quantity, or unit of measure, on a work order that has a parts list and routing attached to it. The Net Change Processing program (R31430) can be launched when you click OK on the Project Workbench form. Values are:

Blank: Do not perform.

1: Perform.

Note: Set the Quantities and Dates processing option in the specified version of Manufacturing Work Order Entry program (P48013) to recalculate parts list and routing information.