Uploading Job Cost Budgets (Release 9.2 Update)

Select Periodic Processing (G31P20), Upload Job Cost Budgets.

To load and update job cost budgets, you use AAI 3130 (Subassembly/Finished Goods). This AAI maps the planned costs from the Project Workbench program to the JD Edwards EnterpriseOne Job Cost system.

Note: The document type that you specify in the processing options must match the document type in the AAI.

To run this batch program, you must select the Interface to Job Cost option in the project attributes; otherwise, the system issues an error message. You can run this program in proof mode to compare the job cost budget to the changes that you applied to the project. When you run the program in final mode, the system updates the Job Cost tables with the budget changes.

If the Update Projected Final Ledger by Subledger/Subledger Type check box is selected for a job that is used by Engineer To Order system and you run the R31P800 program, the system updates the subledger/subledger type with projected final amounts for the job in the F0902 table, where the subledger is the work order number and subledger type is W.