This processing option controls whether the system uses engineering change order verification for the Engineering Change Population program (R30510).
- ECO Approval Validation
Specify whether the system uses engineering change order verification for the Engineering Change Population program (P30510). ECO approval verification lets you update the ECO in final mode only if everyone on the ECO approval list has approved the ECO. If you leave this processing option blank, it is possible that an ECO can be fully incorporated without any approval. Values are:
Blank: Does not verify that the ECO is fully approved before allowing the final mode update.
1: Verifies that the ECO is fully approved before allowing the final mode update.