MRP Pegging Demand

Use Pegging Inquiry (P3412) to determine, or peg, the source of demand for dependent requirements. Pegging Inquiry displays only those parents that contain planned or open orders. Pegging Inquiry enables you to:

  • Display the parent work orders that require a particular item.

  • Trace the source of demand for each item.

  • Display the different levels in a bill of material so that you can peg demand from the beginning level through the parent item.

You can trace the path of dependent requirements up through parent items to the final assembled item and even to the sales order or forecast. You can use this information to determine if you need to reschedule or change orders.