Process

These processing options enable you to specify the variable information that the system uses to regenerate the CRP/RCCP.

1. Under Rated Capacity Percent

Specify the percent under the rated capacity that the system still considers as an underloaded work center. The system displays messages with a status of U (under) for a capacity load that is less than the identified percentage under the rated value.

2. Over Rated Capacity Percent

Specify the percent over the rated capacity that the system displays as overrated and as an overloaded work center. The system displays messages with an O status (over) for capacity loads that are greater than the identified percentage over the rated value.

3. Branch

Specify the branch that the system uses for the CRP/RCCP Planning Regeneration program.

4. Supply/Demand Inclusion Rule

Specify which supply-and-demand inclusion rule the system uses for the generation of an item. Supply and demand inclusion rules define the criteria that the system uses to select active orders for processing.

5. Capacity Mode

Specify which capacity mode the system uses. Values are:

2: Use rough cut capacity planning.

3: Use capacity requirements planning.

6. Unit of Measure

Specify the unit of measure that the system uses for backscheduling the capacity load. The default unit of measure is HR (hour).

7. Roll Up to Dispatch Group

Specify whether the system rolls up multiple work centers to a dispatch group for review. Values are:

Blank: Do not roll up to a dispatch group.

1: Roll up to a dispatch group.

8. Closed Routing Operation Status

Specify the status for closed routing operation. CRP will not calculate loads for operations whose status (OPST) is greater than or equal to this value. If you leave this processing option blank, loads will be calculated for all routing operation steps.