Rescheduling Work Order Operations

You can use the Scheduled Work Order Operations chart to reschedule work order routing operations through a drag-and-drop operation.

Prerequisites

Before you begin:

  • Set the processing options for the P313003X program.

  • Verify that the version ZJDE0002 of the P48013 program has the Quantities and Dates processing option set to 1 to update the parts list and routing information.

To reschedule work order operations:

  1. Access the Work Center Load Review calendar by selecting WC Load Review Calendar from one of the following menus:

    • Daily Order Preparation - Discrete (G3111)

    • Daily Order Preparation - Process (G3113)

    • Daily Rough Cut Capacity Planning (G3312)

    • Daily Capacity Requirements Planning (G3313)

  2. On the Work Center Load Review calendar, right-click a routing operation for the work order for which you want to reschedule the operations, and then select Reschedule WO from the menu.

  3. On the Scheduled Work Order Operations chart, click a routing operation (blue bar), and then drag and drop it to the date you want to move it to.

  4. Click Undo All Changes to revert the requested date to the requested date that was on the work order when you first accessed the P313003X program.

    Note: The system enables the Undo All Changes button only after you perform the drag-and-drop operation. Any custom changes to the start, planned effective, or individual routing step dates will not be honoured when you click Undo All Changes.

When you drag and drop a routing operation, the system moves all other associated routing steps, thereby maintaining the same duration of the work order. After you drag and drop the operation, the system updates the requested date for the work order and the remaining capacity information on the chart.