Reschedule selected production IDs or production schedules with a status of Entered, Firmed, Released, or In Process.

Pages Used to Reschedule Production

Page Name Definition Name Usage

Reschedule Production Page

SF_PRDN_RSCH_REQ

Reschedule selected production IDs or production schedules. Use this page to reschedule multiple production IDs and production schedules simultaneously.

You must have defined at least one production ID or production schedule.

Production Selection Page

SF_PRDN_RELSE_REQ2

Define additional information for production that you want to reschedule.

You must have defined at least one production ID or production schedule.

Reschedule Production Page

Use the Reschedule Production page (SF_PRDN_RSCH_REQ) to reschedule selected production IDs or production schedules.

Use this page to reschedule multiple production IDs and production schedules simultaneously.

Navigation:

Production Control, and then Define Production, and then Production IDs/Schedules, and then Reschedule Production

Field or Control Description

Order Statuses

You can reschedule production with a production status of:

  • Entered

  • Firmed

  • Released

  • In Process

Start Date Range

Choose production for all dates, or enter a range of dates. Any production whose operation is due to start within the actual start date range specified is included.

Production Selection Page

Use the Production Selection page (SF_PRDN_RELSE_REQ2) to define additional information for production that you want to reschedule.

Navigation:

  • Production Control, and then Process Production, and then Release Production, and then Request Prdn Status Change, and then Production Selection

  • Production Control, and then Define Production, and then Production IDs/Schedules, and then Reschedule Production, and then Production Selection

Report Request Parameters

Field or Control Description

Select Production IDs and Select Production Schedules

Indicate whether you want to reschedule production for a particular production ID or schedule, for a range of production IDs, production schedules, or for all production types by selecting both check boxes.

Check Subcontracted Operations

Select to have the system to include production IDs with subcontracted operations.

Run