Changing the Project or Activity Processing Status
You can control incoming transactions at the project or activity level. Projects and activities that have an inactive processing status do not appear in the prompt lists of PeopleSoft cost feeder systems. Inactivating a project or activity effectively shuts off the flow of all transactions to Project Costing for that particular project or activity.
Use the Project Definitions - Status page to select a project status that is associated with the desired processing status.
Use the Activity Definitions - General Information page to modify the activity processing status.
Related Topics