Entering Resource Estimates

This section discusses how to create labor and resource estimate, make adjustments to the bill rate, create expense estimates, enter project control details, add attachments and keywords, and view time and expense summary information.

Pages Used to Enter Labor and Non-Labor Estimates

Page Name Definition Name Usage

Maintain Proposal Page

GM_OPPTY_HDR

Enter general proposal information.

Resource Estimate Page

GM_PM_RSRC_EST

Create or modify project and activity information. You can also view the total bill and cost amounts by activity.

Maintain Version Estimate Detail Page

GM_OPPTY_DTL

Enter resource information.

Bill Estimate - Resource Note Page

GM_SCEN_LINE_NOTE

View or modify information about the resource line.

Current Bill Rate Page

GM_ADJUSTB_SECPNL

Make adjustments to the billing rate.

Project Control Page

GM_OPPTY_PRJCT_CTL

Displays high-level project information. You can change the PeopleSoft Project Costing business unit, type, and manager.

Attachments Page

GM_OPPTY_DOC1

Add documents to the proposal.

Keywords Page

GM_OPPTY_KEYWORD

Add keywords to the proposal.

Summary Page

GM_OPPTY_SUMMARY

View time and expense information at the project, activity, and overall time and expense levels.

Resource Estimate Page

Use the Resource Estimate page (GM_PM_RSRC_EST) to create or modify project and activity information.

You can also view the total bill and cost amounts by activity.

Navigation:

Click the Version link on the Maintain Proposal page.

This example illustrates the fields and controls on the Resource Estimate page. You can find definitions for the fields and controls later on this page.

Resource Estimate page

Project Information

Field or Control Description

Project

Display-only. If you are adding a new project, the system displays NEXT. This automatically generates a system-assigned ID when you save the proposal version. This ID is derived from the Projects table and remains the same throughout the generation process. Upon generation, both the Proposal ID and the Project ID remain in sync with the Contract and Project IDs.

After you run the Contract Generation or the Pre-Spending process, the system turns this field into a link that you can click to access the Project General page in PeopleSoft Project Costing.

Copy Project

Click to access the Copy Project page. The system makes this field display only after you initiate the Contract Generation process.

Note: You can copy projects within a proposal after you run the Pre-Spending process. If the proposal is in a Committed status, however, the system locks down the proposal and you can no longer add projects.

See Understanding the Copy Functionality in PeopleSoft Proposal Management.

Project Control

Click to access the Project Control page, which contains PeopleSoft Project Costing related fields that the system uses in the project creation process.

See Project Control Page.

Activity Summary

Field or Control Description

Activity

Select an activity type to add to the project that you are creating. You can select an activity type from the list or enter a new one (which does not appear in the prompt list). Activity cannot be NEXT. If the activity is not listed, enter a description for the activity in the field. After you run the Contract Generation or the Pre-Spending process, the system turns this field into a link that you can click to access the activity in PeopleSoft Project Costing.

Description

Enter text to describe the activity that you are adding to the project.

Total Cost

Displays the total cost contained in the project across all activities.

Total Bill

Displays the total bill amount contained in the project across all activities.

Margin Percent

Displays as a percentage the difference between the total bill and the total cost for activities (Total Bill − Total Cost) ÷ Total Cost.

Attachments and Keywords

Click to access the Attachments and Keywords pages.

Maintain Version Estimate Detail Page

Use the Maintain Version Estimate Detail page (GM_OPPTY_DTL) to enter resource information.

Navigation:

Click the Activity button in the Activity Summary grid on the Resource Estimate page.

This example illustrates the fields and controls on the Maintain Version Estimate Detail page. You can find definitions for the fields and controls later on this page.

Maintain Version Estimate Detail page
Field or Control Description

Project

Click to access the General Information page.

Pricing Method

Select a value to specify the way in which the system prices the activity. When you run the Generate process, the system passes this information to PeopleSoft Contracts.

  • As Incurred: The as-incurred method is transaction-based. This is the only method that is used for rate-based contract lines. As Incurred applies to the contract line and to both revenue recognition and billing.

  • Fixed: Select to use a fixed-amount contract line for a product or service for which you charge a fixed amount. Fixed-amount contract lines have a price type of Amount or Percent. For fixed-amount contract lines, you associate the contract line with a revenue recognition plan that has a revenue recognition method of Apportionment, Milestone, or Percent Complete. Fixed applies to the contract line and to both revenue recognition and billing.

After you initiate the Pre-Spending or Generate process, this field is display-only.

Product

The entry in this field appears by default from the Contracts BU Setup page and is based on the value you select for the Pricing Method field. If you select a new value in the Pricing Method field, the entry in this field changes accordingly. You define products on the Product Definition pages and in PeopleSoft Contracts. The product you select here is used for billing purposes in PeopleSoft Contracts after your run the Contract Generation process.

See Understanding Products.

Total Cost

Displays the total cost contained in the project for the activity.

Total Bill

Displays the total bill amount contained in the project for the activity.

Calculate Totals

Click to refresh the Total Cost and Total Bill amounts prior to saving the estimate. The system also updates Total Cost and Total Bill amounts when you save.

View Class(es)

Select to view specific Resource Classes on the Resources tab.

Create Resources Team

Select to have the system create a project team on the pages in the Project Team component in PeopleSoft Project Costing. When you save the proposal, the system creates the information in PeopleSoft Project Costing.

Resources - Resources Tab

Field or Control Description

Resource Class

Select a resource class. Options are Asset, Labor, Material, and Other.

Asset or Item

Select an asset or item if you selected Asset or Material resource class.

Resource Name

Enter the person's name or text to describe the team member whom you are adding to the activity. When you create the resources team, the system concatenates the value in the Resource Name field with a system-generated sequence number.

Project Role

Select the role of the person who will work on the activity that you are creating. Project roles are tied to cost and bill rates. When you select a project role, the system automatically fills in the Unit Cost Rate and Unit Bill Rate fields on the Resources - Cost tab.

Note: If the Project Role is set up in the project pricing structure, the system fills in the Unit Cost Rate and Unit Bill Rate fields. If rate is not set up, the system displays a warning message.

Budget Item

Select to identify a budget item with the resource class.

Notes

Click the Notes button to access the Resource Note page.

Resources - Units Tab

Field or Control Description

Start Date

Displays the start date that you entered in the Start Date field on the Maintain Proposal page. You can change the start date here for the project role, but it cannot be greater than the end date.

End Date

Displays the end date that you entered in the End Date field on the Maintain Proposal page. You can change the end date here for the project role, but it cannot be less than the start date.

Unit of Measure

Select a unit of measure.

Hours

Enter the number of hours for the labor resource class row.

Resources - Cost Tab

Field or Control Description

QTY (quantity)

Enter the number of people who will work on the activity who will have the role that you selected.

Unit Cost Rate

Display-only. Indicates the per-hour rate that you are paying the people assigned to the project role.

Unit Bill Rate

Display-only. Indicates the per hour rate that you are billing the customer for the people assigned to the project role.

Actual Bill Rate

Display-only. Indicates the Unit Bill Rate plus or minus any adjustments made on the Current Bill Rate page.

Adjust

Click to access the Bill Estimate - Current Bill Rate page. You can use this page to make adjustments to the bill rate as a flat amount, as a percentage, or as a new rate.

Note: All rates must be greater than zero after the adjustment is made. A rate can not be negative number.

See Current Bill Rate Page.

Bill Estimate - Resource Note Page

Use the Bill Estimate - Resource Note page (GM_SCEN_LINE_NOTE) to view or modify information about the resource line.

Navigation:

Click the Notes button in the Resources grid on the Maintain Version Estimate Detail page.

This example illustrates the fields and controls on the Bill Estimate - Resource Note page.

Bill Estimate - Resource Note page

Current Bill Rate Page

Use the Current Bill Rate page (GM_ADJUSTB_SECPNL) to make adjustments to the billing rate.

Navigation:

Click the Adjust Current Limit Bill Rate button in the Resources - Cost grid on the Maintain Version Estimate Detail page.

This example illustrates the fields and controls on the Bill Estimate - Current Bill Rate. You can find definitions for the fields and controls later on this page.

Bill Estimate - Current Bill Rate
Field or Control Description

Unit Bill Rate

Displays the rate that you are billing for the person who is assigned to the project role.

Adjust Bill Rate

Displays the new rate based on the adjustments you made.

Flat Amount

Enter the number by which to adjust the rate, either a positive or a negative number. When you click OK and then save the page, the system adjusts the rate by the number that you enter. (Adjustment Bill Rate = Bill Rate + Flat Amount)

Percentage

Enter the percentage by which you want to adjust the rate, either a positive or a negative number. When you click OK and then save the page, the system adjusts the rate by the number that you enter. Adjustment Bill Rate = Bill Rate * ( 100 + Percentage )/100

New Rate

Enter the number that you want the system to use to calculate the proposed bill amount for the people who are assigned to the project role. You can only enter a positive number. When you click OK and then save the page, the system changes the rate to the number that you enter. Adjustment Bill Rate = New Rate

No Adjustment

Select this option if you want the system to use the original rate when it calculates the proposed bill amount for the project role.

Apply Rate to all Resource lines with same Region/Project Role

Select this option if you want to apply this rate to all the resource lines with the same region and project role in the current activity.

Apply Rate to current Resource line

Select this option if you want to apply the rate only to the current resource row.

Project Control Page

Use the Project Control page (GM_OPPTY_PRJCT_CTL) to displays high-level project information.

You can change the PeopleSoft Project Costing business unit, type, and manager.

Navigation:

Proposal Management, and then Proposal and Version, and then Maintain Version Estimate

Click the Project Control link on the Resource Estimate page.

This example illustrates the fields and controls on the Project Control page. You can find definitions for the fields and controls later on this page.

Project Control page

Note:

When you initially enter proposal information, the link to this page is not available until you enter information in the Time Estimate and Expense Estimate pages, save the pages, and then return to the Time Estimate page from the Maintain Proposal page.

Detail

Field or Control Description

PC Business Unit (project costing business unit)

Displays the PeopleSoft Project Costing business unit that you selected when you set up the PC business unit. To control the project using another PeopleSoft Project Costing business unit, select a new one. The value in the PC Business Unit field cannot be changed if you have created detail lines for Time or Expense, or when the project team has been created.

Note: You cannot change the PC Business Unit after the system creates a project team, after you initiate Pre-Spending, or after you change the proposal to the Committed status.

Project Type

Select the type of project that you are adding to the proposal. You set up project types in PeopleSoft Project Costing.

Project Manager

Select the name of the person who is the manager of the project.

Attachments Page

Use the Attachments page (GM_OPPTY_DOC1) to add documents to the proposal.

Navigation:

Click the Attachments and Keywords link on the Resource Estimate page.

Field or Control Description

Add Attachment

Click the Add Attachment icon to add a document to the proposal. Click Browse to locate the document on your system and then click Upload to attach the document to the proposal and return to the Attachments page.

Delete Attachment

Click the Delete Attachment button to delete an attached document.

View Attachment

Click the View Attachment button to display the contents of the attached document.

Return to Maintain Version Estimate

Click to return to the Resource Estimate page.

Keywords Page

Use the Keywords page (GM_OPPTY_KEYWORD) to add keywords to the proposal.

Navigation:

Click the Attachments and Keywords link on the Resource Estimate page; then click the Keywords tab.

This example illustrates the fields and controls on the Keywords page. You can find definitions for the fields and controls later on this page.

Keywords page
Field or Control Description

Keyword

Select the word that you want to associate with the proposal.

Add Keyword

Click the Add Keyword button to access the Proposal Key Words page to enter new words that you can then associate with proposals.

Return to Maintain Version Estimate

Click to return to Resource Estimate page.

Summary Page

Use the Summary page (GM_OPPTY_SUMMARY) to view time and expense information at the project, activity, and overall time and expense levels.

Navigation:

Proposal Management, and then Proposal and Version, and then Maintain Version Estimate, and then Summary

This example illustrates the fields and controls on the Summary page (1 of 2). You can find definitions for the fields and controls later on this page.

Summary page (1 of 2)

This example illustrates the fields and controls on the Summary page (2 of 2). You can find definitions for the fields and controls later on this page.

Summary page (2 of 2)

This page summarizes detailed and overall resource information by activity and by project.

Field or Control Description

Summary By

Select a value to change the way that the system displays time and expense information. Options are:

  • Activity.

  • Project.

  • Proposal.