Prerequisites
Before you can create a work order, the following conditions must be met:
-
If selecting a requisition line on the work order, the requisition line status must be Approved or Sourced.
-
The requisition must be filled for automatic work order generation from the sourcing and bid pages.
-
A supplier network must be defined for the business unit.
-
Projects must be defined if Project Costing is installed.
-
Activities must be defined.
-
Service types and services must be defined.
To create the logistical tasks associated with the work order, you should:
-
Define tasks.
-
Define a task group.
-
Associate tasks with the task group.
-
Associate the task group with existing service types.