Here is an example of a due date notification schedule of an evaluation document. In this example, the system is configured to send all three types of email reminders for all evaluation steps using these values: 60 days, 30 days, and 5 days before due date. The column on the far right lists the calculated dates on which due date notifications are sent for each step based on step due dates and the setup of the feature.

Due Date Type or Evaluation Step Step Due Date Who To Notify WHEN DUE DATE NOTIFICATIONS ARE SENT

Define criteria

April 1

Manager, employee, or both

Note: Roles of recipients come from the document template.

January 31 (courtesy, 60 days before due date)

March 2 (warning, 30 days before due date)

March 27 (critical, 5 days before due date)

Nominate participants

May 1

Manager, employee, or both

March 2

April 1

April 26

Complete mid-period checkpoint

June 1

Manager or both

April 2

May 2

May 27

Finalize criteria

October 1

Manager, employee, or both

August 2

September 1

September 26

Employee completes self-evaluation

December 1

Employee

October 2

November 1

November 26

Participant completes peer review

December 5

Participant

October 6

November 5

November 30

Manager completes employee evaluation

December 31

Manager

November 1

December 1

December 26