Reschedule Production Site Cutover
Upgrade-site creation must be complete before you can reschedule the production site cutover.
- On the main page, find the B2C Service that for which you want to change the production-site cutover date.
- Click the Site Operations icon, and then select Manage My Update from the drop-down list.
- Click the Change link next to Cutover Date and Time.
- Type the date in YYYY-MM-DD format, or click the Calendar icon to select a new date.
- From the drop-down list, select either Pacific Daylight Time or Pacific Standard Time. The time you select depends on whether or not the United States is using daylight savings on the day of cutover.
- Click Save.