Migrate Batches to Pipeline

Migrate a batch created in Data Management to the Data Integration Pipeline.

Use the Migrate Batches to Pipeline task to migrate a batch created in Data Management to the Data Integration Pipeline feature.

Note:

For more information about the Pipeline Open Batch Job types, see Using Open Batch Job Types.

To run the migrate batches to the Pipeline:

  1. Click Application, then Jobs, and then Schedule Jobs.

  2. From the Schedule Jobs page, then What type of job is this?, select Integration Maintenance Script.

  3. To schedule an integration maintenance script to run now, see Scheduling Hourly Jobs .

    To schedule an integration maintenance script to run later, see Scheduling a Data Rule or Integration Definition to Run Later in the Job Scheduler.

  4. Click Next.

  5. From Integration Maintenance Script page, click Image shows Select icon. to the right of the Migrate Batches to Pipe task to schedule.

  6. From the Migrate Batches to Pipe page, and then from Batch Name, specify the name of the batch to migrate.

  7. Click OK.