Run the Integration

The Row Based Dates integration we just created is now displayed. To run this integration:

  1. Select Run button (Run Button).


    Row Based Dates integration with the Run button selected

  2. In the Run Integration dialog box, change the Start Period to Jan-21 and the End Period to Dec-21, and then click Run.


    Run Integration dialog box with Run selected

  3. After the integration is complete, you can view the data in the workbench or via a form. For this example, select Workbench.


    Executing Integration dialog box with Workbench selected

  4. Review the integration in the Workbench, and then click Close button (Close button).


    Row Based Dates Workbench data

  5. Click Home button (Home button) to return to the Planning Home page.