Identify Overtime Situations

When resources have activities scheduled outside of their normal working hours, you might want to move those activities to another resource or another time slot.

  1. Click Time View.
  2. In the resource tree, select the bucket or group that contains your resources.
    The routes are displayed
    This figure shows the activities that are outside of normal working hours.
  3. Look for activities that extend beyond the white area into the grey area.
  4. Choose one of these:
    • Move these activities to other resources or other time slots.

    • Move them back to the bucket so that the system can re-route them.

    The white area represents the resource’s shift. The grey area represents time before or after the shift.