Move a Segmentable Activity in a Bucket

If you have created a segmentable activity in a bucket, you can move it to a resource’s route based on the time available in the route. If the destination route has no available time intervals, the application creates one segment of the minimal duration set for the activity type.

  1. Click the hamburger icon and then click Dispatch Console.
  2. Select a bucket or resource in the resource tree.
  3. Select the segmentable activity that you want to move.
  4. Drag and drop the segmentable activity to another route.

    The Move segmentable window opens.

  5. Select one of these options:
    Option Description
    Move all segments starting from date All the segments of the selected segmentable activity are moved to the selected route
    Create segments only for date
    • Segments are created only for the current date. The remaining segmentable activity is left in the bucket.

    • A segment with minimal duration is inserted if the destination route does not have available time interval for that day.

    • One or more feasible segments are inserted if the time is available and the segments with higher duration are removed from the bucket.

    • The remaining duration of the segmentable activity is redistributed in the bucket, creating new segments if necessary.

    Let’s say you move a seven-hour segment from a bucket to a resource and the resource’s route only has time for one 1–hour segment and one 2–hour segment. The application adds the remaining four hours of the activity to the last segment in the bucket or creates a new segment. No segmentable activity segments remain in the bucket for the current date.