Moving Segmentable Activities

You can move and reschedule all the segments, or a single segment of an activity to a specific date.

You can drag and drop an activity or a segment on a resource or route to move the activity. You can use the duration on the hint to estimate whether the destination time slot is enough to move the activity or segment.

For scheduled segmentable activities, the hint displays the duration of the particular segment and for non-scheduled activities, it displays the duration of the entire activity.

You can use this feature to:
  • reassign segments to another resource

  • reschedule a segment to another day

  • reassign multiple segments to another resource

  • reschedule multiple segments to another day

  • move segmentable activity or segment to/from buckets

  • move segmentable activity or segment to the non-scheduled pool

  • move segmentable activity from non-scheduled pool and create scheduled segments for a single day only or generate segments for the entire duration of the activity

You can drag-and-drop activities to perform all these actions, and some others, in the Activities view. The Move link is not supported for segmentable activities. When you drag an activity or a segment, a hint prompts you to drop the activity on a resource or route to which you want to move the activity. The hint also contains the activity or segment duration, so that you can estimate whether the destination time slot is enough to move the activity or segment. For scheduled segmentable activities, the hint shows the duration of the particular segment, while for non-scheduled activities it shows the duration of the entire activity.