Non-scheduled activities are activities that are not assigned to a specific date. You
can view them on the dispatch map to assign them to resources.
-
Open the Dispatch Console and navigate to the Map
view.
-
Select a bucket in the Resource Tree.
-
Click View and select Show non-scheduled
activities. Click Apply.
Non-scheduled activities are displayed as yellow, red, or pink round markers.
Activities that overlap on the map are clustered into one marker with a thicker broader. Only
the activities assigned to the bucket are displayed. Further, the Not
assigned panel is displayed on the map, instead of 'Scheduled'.
-
Click Apply hierarchically.
The non-scheduled activities for the bucket and its child resources are
displayed.
-
To assign an activity to a resource, drag it from the map and drop it to a resource in the
Resource Tree.
-
To move an activity to a bucket, drag and drop it to the required bucket in the Resource
Tree, or in the List view or Time view.
-
To assign multiple activities, drag the clustered marker and drop it to the required
resource or bucket, or in the List view or Time view.