Order of Activities in Bundles

When a bundle is formed, the sequence of activities within the bundle is decided according to these constraints:

  1. activity link constraints

  2. activity priority

  3. service window end

  4. service window start

  5. SLA end

  6. SLA start

  7. activity ID

All bundled activities are analyzed for constraints in the order stated before. If no activities belong to any links, the activity priority, if any, decides the sequence. If no priorities are set for the bundled activities, the activities with the earliest service window end will be placed first, and so on.