Estimate to Complete (ETC) and Estimate at Completion (EAC) in Project Budgets

See what impact your planning has on the final project price.

Project budget view showing Estimate to Complete and Estimate at Completion information.

This feature adds Estimate at Completion (EAC) and Estimate to Complete (ETC) columns to your budgets’ total columns in the budget, actuals, and compare views. When you save changes to your budget, the EAC and ETC fields update to account for the changes.

ETC and EAC values can also be used in several types of crosstabbed and detail reports. In addition, you can use the Inception to Date (ITD) field in reports:

This feature also allows you to set a baseline budget which is used as the main point of comparison against a project’s actual data and other budgets for that project in reporting. A budget with any type of status (open, approved, submitted, archived) can be marked as a baseline.

Note:

Each project can only have one baseline budget.

To enable this feature, contact OpenAir Customer Support. This feature also requires the Project Budgets feature.