Specify the Display Format for Tasks and Resources in Smart View

Use the Display Format for Tasks and Resources in Smart View profile option to specify the display format for tasks and resources in Smart View.

By default, the profile option value is set to Task ID and Resource ID. Set the profile option value to one of the following to view the task IDs and resource IDs along with task or resource name and numbers in Smart View.

Profile Option Value

Display Format in Smart View

Task Name and Resource Name

  • Task name appears followed by :: and task ID

  • Resource name appears followed by :: and resource ID

Task Number and Resource Name

  • Task number appears followed by :: and task ID

  • Resource name appears followed by :: and resource ID

Task Number with Name and Resource Name

  • Task number appears followed by ::, task name, ::, and task ID

  • Resource name appears followed by :: and resource ID

  1. Navigate to the Setup and Maintenance work area and search for the Manage Administrator Profile Values task.

  2. Click Manage Administrator Profile Values.

  3. In the Manage Administrator Profile Values page, enter ORA_PJS_DISP_FRMT_SMRT_VIEW in the Profile Option Code field under the Search : Profile Option section, and click Search.

  4. Select an appropriate value from the Profile Value drop-down list.

  5. Click Save and Close.

  6. Submit the Update Project Performance Data process for those projects for which you want to view the tasks and resources in the selected format in Smart View.

    In Smart View, all tasks and resources are displayed in the selected format for all projects, even if you submit the Update Project Performance data process for a particular project or for all projects.

    Note: You can create a report using Smart View. If you don't want to view the IDs in your report, use the text functions of Excel, such as LEFT and FIND, to filter out the IDs.