How Percent Complete Invoice Amounts Are Calculated
Oracle Fusion Project Billing uses the percent complete invoice method to invoice as progress is measured and recorded.
The Generate Invoice process:
-
Calculates the percent complete amounts
-
Creates invoice events with the percent complete amounts
Prerequisites and Settings That Affect Percent Complete Invoice Amounts
The following prerequisites and settings impact the percent complete invoice for a contract line:
-
The percent complete on the contract line or associated project must be greater than zero.
-
To ensure the percent complete is greater than zero:
-
Ensure the project progress numbers are up to date and then update the progress for the entire contract.
-
Manually enter percent complete.
-
Override percent complete after the update from project progress.
-
-
-
The contract line amount or the funded amount for each project and task associated with the contract line must be greater than zero.
-
The contract line must be assigned to a bill plan that uses the percent complete invoice method.
-
The bill plan contains a calculation level that creates events for the contract line or associated project.
The following table describes the effects of the calculation level selection.
Calculation Level |
Description |
---|---|
Associated project |
The percent complete invoice method creates separate events for each project and task associated with the contract line. Each event contains the project and task associated with the contract line. |
Contract line |
The percent complete invoice method creates one event for the contract line. The event contains the total of all percent complete amount for all projects and tasks associated with the contract line. The event doesn't contain a project or task. |
How Percent Complete Is Calculated
The application performs the following activities when you update the progress:
-
Retrieves all project progress amounts for all tasks for the associated projects of each contract line associated with a percent complete bill plan.
-
Calculates percent complete at the contract line level, if the calculation level in the bill plan is contract line.
-
Calculates percent complete at the associated project and task level, if the calculation level in the bill plan is associated project.
-
Updates the percent complete attributes for all applicable contract lines or associated projects, based on the calculation level selected in the bill plan.
The following examples show how percent complete is calculated at the contract line level and associated project level based on effort and cost.
Contract Line Percent Complete Effort Example
![Percent complete equals left parenthesis, sum of, left parenthesis, baseline budget effort multiplied by Physical Percent Complete, right parenthesis, for every task associated to the contract line, right parenthesis, divided by left parenthesis Sum of Baseline Budget Effort for every task associated to the contract line, right parenthesis.](images/PJB_CLPerComEff_01_20057745.png)
Task |
Baseline Budget Effort |
Physical Percent Complete |
Earned Value Effort |
Percent Complete |
---|---|---|---|---|
1 |
8 |
20 |
160 |
|
1 |
8 |
50 |
400 |
|
Line 1 |
16 |
560 |
35 |
Associated Project Percent Complete Effort Example
![Percent complete equals left parenthesis, sum of, left parenthesis, baseline budget effort multiplied by Physical Percent Complete, right parenthesis, for every subtask that is part of the associated task, right parenthesis, divided by left parenthesis Sum of Baseline Budget Effort for every subtask that is part of the associated task, right parenthesis](images/PJB_APPerComEff_01_20057746.png)
Task |
Baseline Budget Effort |
Physical Percent Complete |
Earned Value Effort |
Percent Complete |
---|---|---|---|---|
1.1 |
2 |
50 |
100 |
|
1.2 |
6 |
10 |
60 |
|
1 |
8 |
160 |
20 |
Contract Line Percent Complete Cost Example
![Percent complete equals left parenthesis, sum of, left parenthesis, baseline budget cost multiplied by Physical Percent Complete, right parenthesis, for every task associated to the contract line, right parenthesis, divided by left parenthesis Sum of Baseline Budget Cost for every task associated to the contract line, right parenthesis.](images/PJB_CLPerComCost_01_20057747.png)
Task |
Baseline Budget Cost |
Physical Percent Complete |
Earned Value Cost |
Percent Complete |
---|---|---|---|---|
1 |
1000 |
20 |
20000 |
|
2 |
500 |
50 |
25000 |
|
Line 1 |
1500 |
45000 |
30 |
Associated Project Percent Complete Cost Example
![Percent complete equals left parenthesis, sum of, left parenthesis, baseline budget cost multiplied by Physical Percent Complete, right parenthesis, for every subtask that is part of the associated task, right parenthesis, divided by left parenthesis Sum of Baseline Budget Cost for every subtask that is part of the associated task, right parenthesis.](images/PJB_APPerComCost_01_20057748.png)
Task |
Baseline Budget Cost |
Physical Percent Complete |
Earned Value Cost |
Percent Complete |
---|---|---|---|---|
1.1 |
250 |
50 |
12500 |
|
1.2 |
750 |
10 |
7500 |
|
1 |
1000 |
20000 |
20 |
|
2.1 |
400 |
60 |
24000 |
|
2.2 |
100 |
10 |
1000 |
|
2 |
500 |
25000 |
50 |
How Percent Complete Invoice Amounts Are Calculated
The following examples show how percent complete invoice amounts are calculated for the contract line and associated project.
Contract Line Percent Complete Amount Example
![Contract Line Percent Complete Invoice Amount equals left parenthesis, left parenthesis, Contract Line Percent Complete multiplied by Contract Line Amount, right parenthesis, minus Sum of Existing Invoice Events, right parenthesis.](images/PJB_MgConInv_PercComEq_CL_01_20057876.png)
Percent Complete |
Contract Line Amount |
Sum of Existing Invoice Events |
Percent Complete Event Amount |
---|---|---|---|
30 |
2000 |
100 |
500 |
Associated Project Percent Complete Amount Example
![Associated Project Percent Complete Invoice Amount equals left parenthesis, left parenthesis, Associated Project Percent Complete, multiplied by Associated Project Funded Amount, right parenthesis, minus Sum of Existing Invoice Events, right parenthesis.](images/PJB_MgConInv_PercComEq_AP_01_20057877.png)
Percent Complete |
Associated Project Funded Amount |
Sum of Existing Invoice Events |
Percent Complete Event Amount |
---|---|---|---|
20 |
1300 |
80 |
180 |
50 |
700 |
20 |
330 |